Hi all,

I'm the project manager of my firm and I manage project timelines and deadlines mostly on Gantt view in Clickup. I set the Gantt view to not show weekends so that we can only see the number of business days needed in a task.

Using this workflow I would need to also add national and local holidays so that non-business days don't count as total days needed in a task, but apparently the settings for national and local holidays are very limited.

I have already tried contacting Clickup support but apparently my plan (Unlimited plan) allows me to set holidays as non working days only in calendar view, and not in Gantt view??? So in a nutshell: my plan allows me to know that there are certain holidays just for curiosity, because I can't set them as non-business days to organize my workflow.

Does anyone know a way around this issue? To me it makes no sense that an absolutely basic feature like setting holidays as non-business days can be set on one type of view and not on another.

Thanks in advance

p.s.: ironically the "unlimited" plan seems pretty limited