▲ 1 r/pmp
An organization hires a project manager experienced with hybrid to improve the organization’s efficiency in delivering projects. The organization currently follows the waterfall approach, completing a task before conducting any quality analysis.
How should the project manager begin improving the organization’s processes?
- A. Maintain processes on active projects, implementing agile approaches in new projects.
- B. Task one of the team members to manage quality analysis in the current projects.
- C. Work with the project management office (PMO) to develop process improvements for all active and future projects.
- D. Work with the project team members to learn the various interdependencies and why the current processes are in place.
u/Efficient-Toe4968 — 8 days ago