An organization hires a project manager experienced with hybrid to improve the organization’s efficiency in delivering projects. The organization currently follows the waterfall approach, completing a task before conducting any quality analysis.

How should the project manager begin improving the organization’s processes?

  • A. Maintain processes on active projects, implementing agile approaches in new projects.
  • B. Task one of the team members to manage quality analysis in the current projects.
  • C. Work with the project management office (PMO) to develop process improvements for all active and future projects.
  • D. Work with the project team members to learn the various interdependencies and why the current processes are in place.