u/DonaldDuckPlus

▲ 2 r/pmp

I’m confused about the correct PMP sequence for handling changes, and I’m seeing conflicting explanations.

Some sources say you must create a change request first, then perform impact analysis, because everything must be formally documented before any work is done.

But in practice (and logically), you would analyze the impact first so you have something meaningful to submit to the Change Control Board (CCB). Otherwise, how can the CCB make a decision without analysis?

So which one is actually correct according to PMI:

  • Perform impact analysis → then create a change request → submit to CCB
  • Create a change request → then perform impact analysis → submit to CCB

Also, is there an official distinction between informal evaluation and formal impact analysis, or is this just interpretation?

Looking for a clear, exam-oriented answer — not just real-world practice.

reddit.com
u/DonaldDuckPlus — 11 days ago
▲ 2 r/pmp

If you were to rank the mock exam resources you used for PMP preparation, what would be your number one, two, three, four, five, and so on?

reddit.com
u/DonaldDuckPlus — 14 days ago
▲ 0 r/pmp

https://preview.redd.it/3gfhm0t661yg1.png?width=995&format=png&auto=webp&s=16ab347dda68c153e96c008bc900f38251f7cff1

The question states that a new product requires adherence to stringent health and safety regulations, and that it is critical to comply with these regulations to ensure public safety.

It then asks: What should the project manager do next to guarantee compliance with these health and safety regulations?

How can assessing and documenting potential compliance risks guarantee compliance with these regulations? This does not make sense.

reddit.com
u/DonaldDuckPlus — 16 days ago
▲ 0 r/pmp

https://preview.redd.it/fxm07f6pt0yg1.png?width=1144&format=png&auto=webp&s=60377850036df343a622deca69a4b758d881a8f4

Hi, can anyone please explain why option D, the Sprint burnup chart, is considered the correct answer?

A sprint burnup chart covers only a single sprint. The answer also uses singular terms—“chart” and “sprint”—not plural. However, the question asks about “remaining tasks for all projects,” not just one sprint.

Additionally, a burnup chart does not clearly show remaining work, whereas a burndown chart does.

reddit.com
u/DonaldDuckPlus — 16 days ago